| Second North East Irrigated Agriculture Project | |||||||||||||||||||||
| Physical Progress as of June 2007 | |||||||||||||||||||||
| District :- Puttalam | |||||||||||||||||||||
| S.No | FocalVillage | Irrigation | Roads | Wells | Multi
Purpose Building |
||||||||||||||||
| Target | Completed | Contract Awarded /Ongoing |
Not Started | Temporarily Susbended |
Target Lengh (K.M) |
Completed | Contract Awarded /Ongoing |
Not Started | Temporarily Susbended |
Target | Completed | Contract Awarded /Ongoing |
Not Started | Temporarily Susbended |
Target | Completed | Contract Awarded /Ongoing |
Not Started | Temporarily Susbended |
||
| 01 | Alankuda | 2.57 | 1 | 2.00 | 2 | 1 | 1 | ||||||||||||||
| 02 | Thigali | 4.30 | 1 | 1 | 1 | ||||||||||||||||
| 03 | Mahagama | 1 | 1 | 5.26 | 1 | 1 | 1 | ||||||||||||||
| 04 | Dangaswewa | 1 | 1 | 5.45 | 1 | 1 | 1 | ||||||||||||||
| 05 | Pullichankulam | 3.18 | 1 | 1 | 1 | ||||||||||||||||
| 06 | Hithayath Nager | 3.83 | 1 | 2.00 | 2 | 1 | 1 | ||||||||||||||
| 07 | Manalthivu | 2.03 | 1 | 1 | 1 | ||||||||||||||||
| 08 | Thambapani | 2.00 | 1 | 2.00 | 2 | 1 | 1 | ||||||||||||||
| 09 | Saliyapura | 1 | 1 | 3.76 | 1 | 1.00 | 1 | 1 | 1 | ||||||||||||
| 10 | Katupulliyankulama | 1 | 4.26 | 1 | 2.00 | 2 | 1 | 1 | |||||||||||||
| Total | 3 | 0 | 3 | 1 | 0 | 37 | 4 | 6 | 0 | 0 | 9 | 2 | 7 | 0 | 0 | 10 | 10 | 0 | 0 | 0 | |