| SECOND NORTH - EAST IRRIGATED AGRICULTURE PROJECT (NEIAP II) |
|
|
|
|
| PROCUREMENT PLAN
FOR WORKS |
|
| IDA CREDIT NO.
3935 CE Project ID : P086747 |
|
|
|
|
|
| |
SL No. |
Component No. |
Package No. |
Descriptions of Works |
Estimated Cost
(Rs.in Mn) |
Method of Procurement
ICB/NCB/
NS/DC |
Preperation of Bid
Documents
(Date) |
Bank's No Objection to
Bidding Documents (Date)** |
Bids |
Contract Award decided
(Date / Value / Currency) |
Bank's No Objection to
Contract Award
(Date)** |
Contract Signed
(Date/value/Currency) |
Contract No. |
Name of
Contractor/Nationality & ZIP Code |
** WBR No. |
Date of Completion of
Contract |
Expenditure incurred to
Date |
|
| Invitation (Date) |
Opened
on (date) |
|
| 1 |
2 |
3 |
4 |
5 |
6 |
7 |
8 |
9 |
10 |
11 |
12 |
13 |
14 |
15 |
16 |
17 |
18 |
|
| PROCUREMENT PLAN FOR WORKS |
|
|
1 |
1 |
|
Irrigation Scheme
(30 Nos) |
150 |
NCB |
25.04.05 |
25.05.05 |
08.06.05 |
08.07.05 |
30.07.05 |
07.08.05 |
20.08.05 |
|
|
|
|
|
|
| R |
For the
details please refer Districts Procurement Plans |
|
| A |
|
|
2 |
1 |
|
Irrigation Scheme
(30 Nos) |
60 |
DC |
25.04.05 |
25.05.05 |
08.06.05 |
08.07.05 |
30.07.05 |
07.08.05 |
20.08.05 |
|
|
|
|
|
|
| R |
For the
details please refer Districts Procurement Plans |
|
| A |
|
|
3 |
1 |
|
Rural Roads
(50 Villages) |
150 |
NCB |
25.04.05 |
25.05.05 |
08.06.05 |
08.07.05 |
30.07.05 |
07.08.05 |
20.08.05 |
|
|
|
|
|
|
| R |
For the
details please refer Districts Procurement Plans |
|
| A |
|
|
4 |
1 |
|
Rural Roads
(50 Villages) |
100 |
DC |
25.04.05 |
25.05.05 |
08.06.05 |
08.07.05 |
30.07.05 |
07.08.05 |
20.08.05 |
|
|
|
|
|
|
| R |
For the
details please refer Districts Procurement Plans |
|
| A |
|
|
5 |
1 |
|
Drinking water wells
(50 villages) |
20 |
DC |
25.04.05 |
25.05.05 |
08.06.05 |
08.07.05 |
30.07.05 |
07.08.05 |
20.08.05 |
|
|
|
|
|
|
| R |
For the
details please refer Districts Procurement Plans |
|
| A |
|
|
6 |
1 |
|
Community building
(50 villages) |
50 |
DC |
25.04.05 |
25.05.05 |
08.06.05 |
08.07.05 |
30.07.05 |
07.08.05 |
20.08.05 |
|
|
|
|
|
|
| R |
For the
details please refer Districts Procurement Plans |
|
| A |
|
|
7 |
1 |
|
Ponds, Dykes & Drainage Canals in Jaffna |
40 |
NCB |
25.04.05 |
25.05.05 |
08.06.05 |
08.07.05 |
30.07.05 |
07.08.05 |
20.08.05 |
|
|
|
|
|
|
| R |
For
the details please refer Jaffna District Procurement Plan |
|
| A |
|
|
8 |
2 |
|
Irranamadu Scheme |
1000 |
NCB |
25.04.05 |
25.05.05 |
08.06.05 |
08.07.05 |
30.07.05 |
07.08.05 |
20.08.05 |
|
|
|
|
|
|
| R |
For
the details please refer Kilinochchi District Procurement Plan |
|
| A |
|
|
9 |
2 |
|
Giants Tank |
200 |
NCB |
25.04.05 |
25.05.05 |
08.06.05 |
08.07.05 |
30.07.05 |
07.08.05 |
20.08.05 |
|
|
|
|
|
|
| R |
For
the details please refer Mannar District Procurement Plan |
|
| A |
|
|
10 |
1 |
|
Valukkaiaru Scheme in Jaffna |
200 |
NCB |
25.04.05 |
25.05.05 |
08.06.05 |
08.07.05 |
30.07.05 |
07.08.05 |
20.08.05 |
|
|
|
|
|
|
| R |
For
the details please refer Jaffna District Procurement Plan |
|
| A |
|
|
11 |
2 |
|
Allai Extension Rehabilitation |
200 |
NCB |
25.04.05 |
25.05.05 |
08.06.05 |
08.07.05 |
30.07.05 |
07.08.05 |
20.08.05 |
|
|
|
|
|
|
| R |
For
the details please refer Trincomalee District Procurement Plan |
|
| A |
|
|
12 |
2 |
|
Rugam Tank Rehabilitation |
200 |
NCB |
25.04.05 |
25.05.05 |
08.06.05 |
08.07.05 |
30.07.05 |
07.08.05 |
20.08.05 |
|
|
|
|
|
|
| R |
For
the details please refer Batticaloa District Procurement Plan |
|
| A |
|
|
13 |
2 |
|
Karavahu Drainage Rehabilitation |
100 |
NCB |
25.04.05 |
25.05.05 |
08.06.05 |
08.07.05 |
30.07.05 |
07.08.05 |
20.08.05 |
|
|
|
|
|
|
| R |
For
the details please refer Amparai District Procurement Plan |
|
| A |
|
|
14 |
2 |
|
Construction of RE's Office
(4 Nos) |
10 |
NCB |
25.04.05 |
N/A |
08.06.05 |
08.07.05 |
30.07.05 |
07.08.05 |
20.08.05 |
|
|
|
|
|
|
| R |
For the
details please refer Districts Procurement Plans |
|
| A |
|
|
15 |
3 |
|
Agriculture Buildings |
23 |
NCB |
25.04.05 |
N/A |
08.06.05 |
17.06.05 |
20.08.05 |
N/A |
30.08.05 |
|
|
|
|
|
|
| R |
For the
details please refer Districts Procurement Plans |
|
| A |
|
|
16 |
4 |
|
Construction of Soil Laboratory
(6 Nos) |
12 |
NCB |
25.04.05 |
N/A |
08.06.05 |
08.07.05 |
30.07.05 |
N/A |
20.08.05 |
|
|
|
|
|
|
| R |
For the
details please refer Districts Procurement Plans |
|
| A |
|
|
17 |
4 |
|
Repairs to Build.& Quarters
(8 Nos) |
24 |
NCB |
25.04.05 |
N/A |
08.06.05 |
08.07.05 |
30.07.05 |
N/A |
20.08.05 |
|
|
|
|
|
|
| R |
For the
details please refer Districts Procurement Plans |
|
| A |
|
|
18 |
4 |
|
Construction of PMU Building |
40 |
NCB |
25.04.05 |
25.05.05 |
08.06.05 |
08.07.05 |
30.07.05 |
07.08.05 |
20.08.05 |
|
|
|
|
|
|
| R |
25.04.07 |
25.05.07 |
08.06.07 |
08.07.07 |
30.07.07 |
07.08.07 |
20.08.07 |
|
|
|
|
|
|
| R |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
19 |
4 |
|
Construction of Circuit Bangalow |
8 |
NCB |
25.04.05 |
01.05.05 |
08.06.05 |
08.07.05 |
30.07.05 |
10.08.05 |
20.08.05 |
|
|
|
|
|
|
| R |
25.04.07 |
25.05.07 |
08.06.07 |
08.07.07 |
30.07.07 |
07.08.07 |
20.08.07 |
|
|
|
|
|
|
| R |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
20 |
4 |
|
Repairs to Soil Lab Building
( 4 Nos) |
4 |
NCB |
25.04.05 |
N/A |
08.06.05 |
08.07.05 |
30.07.05 |
N/A |
20.08.05 |
|
|
|
|
|
|
| R |
For the
details please refer Districts Procurement Plans |
|
| A |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| IRRIGATION SCHEME
(Reference No: 1 in master procurement plan) |
|
| IRRIGATION SCHEME
(DC) (Reference No: 2 in master procurement plan) |
|
| RURAL ROADS
(Reference No: 3 in master procurement plan) |
|
| RURAL ROADS (DC)
(Reference No: 4 in master procurement plan) |
|
| DRINKING WATER
WELLS (DC) (Reference No: 5 in master procurement plan) |
|
| COMMUNITY BUILDING
(DC) (Reference No: 6 in master procurement plan) |
|
| PONDS, DYKES &
DRAINAGE CANALS IN JAFFNA (Reference No: 7 in master procurement plan) |
|
| IRRANAMADU SCHEME
(Reference No: 8 in master procurement plan) |
|
| GIANTS TANK
(Reference No: 9 in master procurement plan) |
|
| VALUKKAIARU SCHEME
IN JAFFNA (Reference No: 10 in master procurement plan) |
|
| ALLAI EXTENSION
REHABILITATION (Reference No: 11 in master procurement plan) |
|
| RUGAM TANK
REHABILITATION (Reference No: 12 in master procurement plan) |
|
| KARAVAHU DRAINAGE
REHABILITATION (Reference No: 13 in master procurement plan) |
|
| CONSTRUCTION OF
RE'S OFFICE (Reference No: 14 in master procurement plan) |
|
| AGRICULTURE
BUILDINGS (Reference No: 15 in master procurement plan) |
|
| CONSTRUCTION OF
SOIL LABORATORY (Reference No: 16 in master procurement plan) |
|
| REPAIRS TO
BUILD.& QUARTERS (Reference No: 17 in master procurement plan) |
|
| CONSTRUCTION OF
PMU BUILDING (Reference No: 18 in master procurement plan) |
|
| CONSTRUCTION OF
CIRCUIT BANGALOW (Reference No: 19 in master procurement plan) |
|
| REPAIRS TO SOIL
LAB BUILDING (Reference No: 20 in master procurement plan) |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|