Second North East Irrigated Agriculture Project
Physical Progress as of  June  2007
District :- Polonnaruwa
S.No FocalVillage Irrigation Roads Wells Multi Purpose
Building
    Target Completed Contract
Awarded
/Ongoing
Not  Started Temporarily
Susbended
Target
Lengh (K.M)
Completed Contract
Awarded
/Ongoing
Not Started Temporarily
Susbended
Target Completed Contract
Awarded
/Ongoing
Not Started Temporarily
Susbended
Target Completed Contract
Awarded
/Ongoing
Not Started Temporarily
Susbended
01 Galthalawa 1   1     5.879 1       2 2       1 1      
02 Hathareskotuwa 1       1 2.23 1       4   4     1   1    
03 Irigeoya           1.56   1     1   1     1 1      
04 Maharathmale 1       1 3.56 1       -         1   1    
05 Jayabima 1       1 2.087   1     1   1     1   1    
06 Akbarpura 1     1   3.87     1   -         1   1    
07 Pamburana 1     1   2.82   1     1   1     1   1    
08 Mailagashandiya 1       1 2.655 1       3   3     1   1    
09 Viharagama 1       1 2.2     1   1     1   1   1    
10 Kandakadu 1   1     -         -         1 1      
Total 9   2 2 5 26.861 4 3 2 0 13 2 10 1 0 10 3 7 0 0