The project is under way in 349 focal villages in all eight districts of North & East province and 47 selected border villages of the neighbouring four districts and completed the following activities as of June 2004.

 
1

The project has rehabilitated 214 irrigation schemes.

2

Improved service capacity of about 861.74 km of village rural roads

3

Constructed about 519 Nos of safe drinking water wells.

4

Under livelihood support activities, self- employment & income generating activities have been provided for some 14,641 families and the project has constructed about 245 Nos of community centres.